Corby Power Station Contamination Assessment

Intrusive ground investigation along a former above-ground diesel pipeline route to assess the contamination status of Tata Steel land before infrastructure removal.

Corby, Northamptonshire Industrial / Contaminated Land Corby Power / Tata Steel
Corby Power Station Contamination Assessment - EnviroSolution case study
The Project

The Project

EnviroSolution was commissioned by Corby Power to assess land owned by Tata Steel that had previously accommodated an above-ground pipeline used to transport diesel oil. Before the pipeline was installed, the route had also been occupied by railway sidings. The assessment was required before the redundant infrastructure was removed and the land reinstated.

The Challenge

The Challenge

The investigation needed to distinguish any contamination associated with the former diesel pipeline from the site's earlier industrial and railway history.

The Solution

The Solution

A Geo-Environmental Engineer completed an intrusive ground investigation and collected representative soil samples along the pipeline route. Samples were analysed by a UKAS-accredited laboratory for Diesel Range Organics and interpreted using TPH Criteria Working Group standards. The results indicated low-level contamination dominated by heavier-end hydrocarbons rather than evidence of diesel loss from the pipeline.

The Benefit

The Benefit

Rapid mobilisation and clear interpretation allowed Corby Power and Tata Steel to proceed with greater confidence. The findings reduced uncertainty around remediation requirements and supported the planned infrastructure removal.

Need similar support?

Tell us what has happened and we’ll help identify the right next step.

Send the site address, planning wording, photographs, deadlines and any previous reports so the team can advise quickly.